Hello, as part of a 7.4 upgrade project we want to migrate NW 7.01 NWDI/JDI to another system with help of the System Copy Tool.
We want to make it before to a test/dummy system.
CBS an CMS are on the original system but it is connected to an external SLD on BI production system. The questions is how can I make this test/dummy system copy without affecting to the original NWDI in source system.
I`ve checked checked the following note:
877029 - System Copy for NWDI
and this article:
https://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/70ee5ab2-8d7a-2c10-d88b-dbe2fdf666e7
I've reviewed scn messages too but I'm not absolutelly sure about how to make it.
For test/dummy system copy, should I use 'COPY' option for DTR? but CBS and CMS do NOT support the option 'COPY' could this affect to the original NWDI? Should I connect it to another SLD?
In the other hand, for the real system copy I understand that I should use 'MOVE' option also for DTR.
I want to ensure that test/dummy system copy does NOT afect original NWDI system.
thanks in advance.
Best regards.